"ME – Mattawoman Natural Gas-fired Power Plant 990 MW – Maryland - Project Profile" contains information on the scope of the project including project overview and location. The profile also details project ownership and funding, gives a full project description, as well as information on contracts, tendering and key project contacts.

The "ME – Mattawoman Natural Gas-fired Power Plant 990 MW – Maryland - Project Profile" is part of Timetric's database of 82,000+ construction projects. Our database includes a 10+ year archive of completed projects, full coverage of all global projects with a value greater than $25 million and key contact details for project managers, owners, consultants, contractors and bidders.

Summary

Mattawoman Energy LLC (ME), a wholly owned subsidiary of Panda Power Funds, is planning to undertake a gas-fired power plant in Prince George’s County, Maryland, Washington, DC, the US.

The project involves the construction of a 990MW, 2-on-1 gas-fired combined-cycle facility featuring two H-class combustion turbines and two duct-fired heat recovery steam generators on 36ha area.

The project includes the construction of a powerhouse to install the turbines and generators, substations, water and fuel storage tanks, combustion units, cooling towers, heat recovery units and other related facilities and the laying of water and transmission lines.

In October 2012, ME acquired the land at a worth of US$7.5 million for the development of the project. In July 2013, the project secured planning approvals from Maryland Public Service Commission.

In March 2015, ME has upgraded the project’s capacity from 859MW to 990MW.

ME is in the process of securing a certificate of public convenience and necessity (CPCN) and a public hearing on air quality is scheduled to be held on August 17, 2015.

On November 13, 2015, ME secured final approval from the Maryland Public Service Commission.

In June 2017, ME will receive US$445 million funds from Hana Financial Investment Co.

Planning activities are underway.

Scope

The project involves the construction of a 990MW, 2-on-1 gas-fired combined-cycle facility on a 36ha area in Prince George’s County, Maryland, the US.

The US$660 million project includes the following:

1. Construction of a powerhouse to install the steam turbines and generators

2. Construction of combustion units

3. Construction of water and fuel storage tanks

4. Construction of heat recovery units

5. Construction of a cooling tower

6. Construction of substations

7. Installation of Siemens model combustion turbines

8. Installation of two duct-fired heat recovery steam generators

9. Laying of transmission lines

Reasons To Buy

  • Gain insight into the project.
  • Monitor the latest project developments.
  • Identify key project contacts.


1.Key Statistics
2.Key Dates
3.Sector
4.Operating metrics
5.Tender Information
6.Scope
7.Description
8.Latest update
9.Background
10.Key Contacts
11.General News, Project News
12.Appendix

Download our eBook: How to Succeed Using Market Research

Learn how to effectively navigate the market research process to help guide your organization on the journey to success.

Download eBook

Share this report