"FSLR – Jeffersonville Solar Power Plant 200 MW – Georgia - Project Profile" contains information on the scope of the project including project overview and location. The profile also details project ownership and funding, gives a full project description, as well as information on contracts, tendering and key project contacts.
The "FSLR – Jeffersonville Solar Power Plant 200 MW – Georgia - Project Profile" is part of Timetric's database of 82,000+ construction projects. Our database includes a 10+ year archive of completed projects, full coverage of all global projects with a value greater than $25 million and key contact details for project managers, owners, consultants, contractors and bidders.
Summary
First Solar Inc. (FSLR) is planning to construct a solar power plant on 809ha of land in Georgia, the US.
The project includes the construction of 200MW solar power plant on 809ha. It includes the construction of a substation, the installation of solar panels, transformers and batteries, and the laying of transmission lines.
Construction is expected to commence in the fourth quarter of 2018 and is scheduled for completion in the fourth quarter of 2019.
As of February 2018, planning activities are underway.
Scope
The project involves the construction of a 200MW solar power plant in Jeffersonville, Georgia, the US.
The US$350 million project includes the following:
1. Construction of a substation
2. Installation of a solar panels
3. Installation of transformers
4. Installation of batteries
5. Laying of transmission lines