TAQA/CWM – Waste-to-Energy Power Plant 100 MW – Abu Dhabi - Project Profile

TAQA/CWM – Waste-to-Energy Power Plant 100 MW – Abu Dhabi - Project Profile

Synopsis

"TAQA/CWM – Waste-to-Energy Power Plant 100 MW – Abu Dhabi - Project Profile" contains information on the scope of the project including project overview and location. The profile also details project ownership and funding, gives a full project description, as well as information on contracts, tendering and key project contacts.

The "TAQA/CWM – Waste-to-Energy Power Plant 100 MW – Abu Dhabi - Project Profile" is part of Timetric's database of 82,000+ construction projects. Our database includes a 10+ year archive of completed projects, full coverage of all global projects with a value greater than $25 million and key contact details for project managers, owners, consultants, contractors and bidders.

Summary

Abu Dhabi National Energy Company PJSC (TAQA) and the Centre of Waste Management Abu Dhabi (CWM) are jointly planning to undertake the Waste-to-Energy Power Plant project in the UAE.

The project involves the construction of a waste-to-energy facility with a capacity to process up to 1,000,000 tonnes of landfill waste and produce 100MW of power.

The project will include the construction of a cooling tower, a flue-gas stack, a water treatment system and a trash storage bunker, the installation of a biomass boiler, steam turbine generator, condenser, cooling water system, scrubbers, fly ash handling system, acid gas removal system, nitrogen oxide removal system, particulate removal system and a transformer, and the laying of transmission lines.

Ramboll has been appointed as an engineering consultant, Atkins as an environmental consultant, and Linklaters LLP as the legal adviser.

In June 2012, TAQA and CWM signed a memorandum of understanding (MoU) for the joint development of the project.

In February 2013, TAQA appointed HSBC as the financial adviser of the project.

On February 28, 2013, TAQA invited companies to submit the request for qualifications (RFQ) for the engineering, procurement, and construction (EPC) contract with submission deadline as March 15, 2013. However, TAQA waiting for necessary approvals from the government, following which a request for proposal (RFP) will be issued.

Planning activities are underway.

Scope

The project involves the construction of a 100MW waste-to-energy facility with a capacity to process up to 1,000,000 tonnes of landfill waste in Abu Dhabi, the UAE.

The US$850 million project includes the following:

1. Construction of a cooling tower

2. Construction of a flue-gas stack

3. Construction of water treatment system

4. Construction of trash storage bunker

5. Installation of scrubbers

6. Installation of fly ash handling system

7. Installation of a biomass boiler

8. Installation of particulate removal system

9. Installation of acid gas removal system

10. Installation of nitrogen oxide removal system

11. Installation of condenser and a cooling water system

12. Laying of transmission lines

Reasons To Buy

  • Gain insight into the project.
  • Monitor the latest project developments.
  • Identify key project contacts.


1.Key Statistics
2.Key Dates
3.Sector
4.Operating metrics
5.Tender Information
6.Scope
7.Description
8.Latest update
9.Background
10.Key Contacts
11.General News, Project News
12.Appendix

Download our eBook: How to Succeed Using Market Research

Learn how to effectively navigate the market research process to help guide your organization on the journey to success.

Download eBook

Share this report