"GoKP – Chitral-Lower Dir Transmission Line – Khyber Pakhtunkhwa - Project Profile" contains information on the scope of the project including project overview and location. The profile also details project ownership and funding, gives a full project description, as well as information on contracts, tendering and key project contacts.
The "GoKP – Chitral-Lower Dir Transmission Line – Khyber Pakhtunkhwa - Project Profile" is part of Timetric's database of 82,000+ construction projects. Our database includes a 10+ year archive of completed projects, full coverage of all global projects with a value greater than $25 million and key contact details for project managers, owners, consultants, contractors and bidders.
Summary
The Government of Khyber Pakhtunkhwa (GoKP) is planning to build a transmission line in Khyber Pakhtunkhwa, Pakistan.
The project involves the construction of a 225km, 500kV transmission line from Chitral to Lower Dir. It includes construction of power stations, switching stations, controlling units and related infrastructure, the installation of transformers and generators, and the laying of transmission lines.
In November 2017, the federal government ignored the proposed Chakdara grid station by GoKP for financing under CPEC.
Planning activities underway and GoKP is waiting for necessary approvals to proceed with the development works.
Scope
The project involves the construction of a 225km, 500kV transmission line from Chitral to Lower Dir in Khyber Pakhtunkhwa, Pakistan.
The US$112 million project includes the following:
1. Construction of power stations
2. Construction of switching stations
3. Construction of controlling units
4. Installation of transformers and generators
5. Laying of transmission lines