Market Research Logo

JSPL – Angul Integrated Steel and Power Plant – Odisha - Project Profile

JSPL – Angul Integrated Steel and Power Plant – Odisha - Project Profile

Synopsis

"JSPL – Angul Integrated Steel and Power Plant – Odisha - Project Profile" contains information on the scope of the project including project overview and location. The profile also details project ownership and funding, gives a full project description, as well as information on contracts, tendering and key project contacts.

The "JSPL – Angul Integrated Steel and Power Plant – Odisha - Project Profile" is part of Timetric's database of 82,000+ construction projects. Our database includes a 10+ year archive of completed projects, full coverage of all global projects with a value greater than $25 million and key contact details for project managers, owners, consultants, contractors and bidders.

Summary

Jindal Steel & Power Ltd (JSPL) is undertaking the construction of an Integrated Steel and Power Plant project in Odisha, India.

The project involves the construction of a 12.5 million tonnes per annum (MTPA) steel plant and a captive power plant. It will be executed in two phases

The first phase includes the construction of a 6MTPA integrated steel plant along with a 810MW captive power plant.

The second phase includes the construction of a 6.5MTPA steel plant and a 1,600MW captive power plant.

The project includes the rehabilitation of a residential colony, the construction of a waste water treatment facility, coal storage units and related road infrastructures and the laying of pipelines.

JSPL is utilizing DRI-BF-EAF route technology for manufacturing steel and has signed an agreement with Lurgi Sasol Technology Company, South Africa; Siemens VAI Metals Technologies GmbH & Co, Austria; and Danieli & C. Officine Meccaniche S.P.A., Italy, for providing technology service.

JSPL has signed an agreement with Lurgi Sasol Technology Company, South Africa, for providing technology for coal gasification.

A private railway siding is being constructed in proposed integrated steel and power plant project and detail survey report of the private railway siding was prepared by RITES and construction contract for of railway siding was awarded to ARSS Infrastructure Projects Ltd.

In 2007, the environmental clearance was given for the project, however due to construction activities in the non allotted land, the project has received notice in November 2010 which received conditional clearance in February 2011.

In March 2011, Ministry of Environment and Forests again sent notice for violating the forest rules.

In April 2012, Leighton Welspun Contractors Pvt Ltd (LWIN) was appointed as the construction contractor for the project.

In June 2012, Essar Projects Ltd was appointed as a general contractor for the first phase. The scope of contract covers the construction of a steel melting shop, raw material handling system, a coal gasification plant and a direct reduced iron plant.

In August 2013, construction works of 2MTPA capacity steel melting shop (SMS), a part of first phase of 6MTPA integrated steel plant are nearing completion.

As of May 2014, construction works of 1.5MTPA capacity steel melting shop, a part of first phase of 6MTPA integrated steel plant was completed.

The 810MW captive power plant of first phase and 2MTPA capacity steel melting shop has commissioned by the fourth quarter of 2014.

As of July 2015, JSPL is awaiting to take possession of 728ha of land required to start the construction on the remaining 4MTPA capacities for the first phase of the project.

On September 10, 2015, a meeting was held between JSPL, Birankeswar Shilpanchal Kshyatigrasta Praja Sangha and Maa Kaluni PrajaSangha.

As of October 2015, 728ha of land was acquired by JSPL for the project.

On May 27, 2017, construction works were completed in the first phase of the project.

As of June 2017, planning activities are underway.

Stakeholder Information:
Planning Authority: Ministry of Steel, India & Ministry of Environment and Forests, India
Consultant: Lurgi Sasol Technology Company, South Africa
EPC Contract (Rail Siding): ARSS Infrastructure Projects Ltd
EPC Contract: Leighton Welspun Contractors Pvt Ltd, Essar Projects Ltd

Scope

The project involves the construction of a steel plant and a captive power plant on a 2,428ha of land near Chhendipada in Angul in Odisha, India.

The US$10,000 million project includes the following:

1. Construction of 12.5MTPA steel production plant

2. Construction of a 2,410MW captive power plant

3. Rehabilitation of housing colony

4. Construction of waste water treatment plants

Reasons To Buy

  • Gain insight into the project.
  • Monitor the latest project developments.
  • Identify key project contacts.


1.Key Statistics
2.Key Dates
3.Sector
4.Operating metrics
5.Tender Information
6.Scope
7.Description
8.Latest update
9.Background
10.Key Contacts
11.General News, Project News
12.Appendix

Download our eBook: How to Succeed Using Market Research

Learn how to effectively navigate the market research process to help guide your organization on the journey to success.

Download eBook

Share this report