Market Research Logo

TLP – Swansea Bay Tidal Power Plant 320 MW – UK - Project Profile

TLP – Swansea Bay Tidal Power Plant 320 MW – UK - Project Profile

Synopsis

"TLP – Swansea Bay Tidal Power Plant 320 MW – UK - Project Profile" contains information on the scope of the project including project overview and location. The profile also details project ownership and funding, gives a full project description, as well as information on contracts, tendering and key project contacts.

The "TLP – Swansea Bay Tidal Power Plant 320 MW – UK - Project Profile" is part of Timetric's database of 82,000+ construction projects. Our database includes a 10+ year archive of completed projects, full coverage of all global projects with a value greater than $25 million and key contact details for project managers, owners, consultants, contractors and bidders.

Summary

Tidal Lagoon Power Ltd (TLP) is planning to undertake the construction of the Swansea Bay Tidal Power Plant in the UK.

The project involves the construction of a 320MW tidal power plant. The project will include an oyster-shaped offshore visitor center and national triathlon and water sports facilities.

The project includes the installation of 16 turbine housings, sluice gates, flood doors, rails, electrical controls and hydraulics, the construction of precast concrete components, 9.5km seawall, 10km sea reef, education center, art center, a visitor center, ancillary buildings and other related infrastructure facilities.

In April 2013, Intertek Energy & Water consultancy services has been appointed as a Study Consultant for the project. KGAL has been appointed as the M&E design specialist.

LDA Design and Porta Planning has been appointed as Master Planner.

In June 2013, Alstom signed a Memorandum of Understanding with TLP to design and build the generating units. Alstom will work in partnership with TLP to create an optimal solution for the low head tidal lagoon.

In July 2013, Costain, Atkins, and Van Oord reached agreements to partner with TLP to design, build and deliver the project. Costain will work alongside all partners to coordinate and manage delivery.

In October 2013, SLR Consulting was appointed to provide strategic planning advice for the project. SLR will support TLP through the provision of specialist Nationally Significant Infrastructure Project (NSIP) consenting advice as well as prepare the supporting Planning Statement.

Tencate will supply the Geotubes, which are filled with dredged material from within the lagoon footprint, largely sands and gravels, which are pumped in hydraulically. The water from this hydraulic pumping process is then forced out through the permeable geotextile membrane leaving very strong, compact sand-filled tubes which form the core structure of the wall.

FaulknerBrowns LLP has been appointed as an Architect for International watersport & hatchery center and Juice Architects for Visitor Centre.

In February 2014, TLP submitted planning application to National Infrastructure Planning for approvals.

The application has reached the required standards to proceed to public examination before being determined by the Secretary of State for Energy & Climate Change.

On March 6, 2014, the planning application was accepted for consideration for consent to build tidal lagoon.

The local authorities, City & County of Swansea and Neath Port Talbot County Borough were invited to submit ‘Local Impact Reports’ (LIR) setting out their views.

In August 2014, Atkins has been appointed as the Consulting Engineer.

In October 2014, Prudential Financial was named as one of the investors investing US$161 million.

On February 5, 2015, InfraRed Capital Partners joined as one of the investors, by investing US$152 million.

On February 10, 2015, Andritz and GE have signed an advanced works agreement with a total value of around US$452.5 million. Andritz will fulfill around US$282.8 million of the contract, with GE claiming the remainder.

Laing O'Rourke has been appointed as contractor for turbine house and water flow sluice.

On June 4, 2015, China Harbour Engineering Company (CHEC) secured US$458 million marine works construction contract.

On June 9, 2015, TLP secured approval from the Department for Energy & Climate Change.

On July 29, 2015, the developer has submitted plans for a water sports center. The water sports center, also known as the western landfill building, was not included in the planning consent given by Planning Authority last month.

The planning Authority might require some further information before examining the application.

The developer has also been required to submit plans on areas such as pollution prevention, piling methods, and noise monitoring. An application for a cable link from the docks to a Baglan Bay substation is in with Neath Port Talbot and Swansea councils.

In May 2016, the contract of China Harbour Engineering Company (CHEC) was terminated and TLP will retender for marine works contract.

In June 2016, TLP secured US$134.2 million investment for the development.

Subject to the marine license from the Natural Resources Wales. The final decision is expected in 2017. Construction is scheduled to commence in 2018.

Scope

The project involves the construction of a tidal power plant with a rated capacity of 320MW in Swansea Bay, the UK.

The US$1,622 million project includes the following:

1. Construction of concrete components

2. Construction of an oyster-shaped offshore visitor centre

3. Construction of national triathlon and water sports facilities

4. Construction of ancillary buildings

5. Construction of 9.5km sea wall

6. Construction of 10km seareef

7. Construction of an Education center

8. Construction of an Art center

9. Construction of other related infrastructure facilities

10. Installation of turbines

11. Installation of sluice gates

12. Installation of flood doors

13. Installation of rails

14. Installation of electrical controls

15. Installation of hydraulics

Reasons To Buy

  • Gain insight into the project.
  • Monitor the latest project developments.
  • Identify key project contacts.


1.Key Statistics
2.Key Dates
3.Sector
4.Operating metrics
5.Tender Information
6.Scope
7.Description
8.Latest update
9.Background
10.Key Contacts
11.General News, Project News
12.Appendix

Download our eBook: How to Succeed Using Market Research

Learn how to effectively navigate the market research process to help guide your organization on the journey to success.

Download eBook

Share this report