Steelhead/HFN – Sarita Bay LNG Export Facility – British Columbia - Project Profile

Synopsis

"Steelhead/HFN – Sarita Bay LNG Export Facility – British Columbia - Project Profile" contains information on the scope of the project including project overview and location. The profile also details project ownership and funding, gives a full project description, as well as information on contracts, tendering and key project contacts.

The "Steelhead/HFN – Sarita Bay LNG Export Facility – British Columbia - Project Profile" is part of Timetric's database of 82,000+ construction projects. Our database includes a 10+ year archive of completed projects, full coverage of all global projects with a value greater than $25 million and key contact details for project managers, owners, consultants, contractors and bidders.

Summary

Steelhead LNG Corp. (Steelhead) and Huu-ay-aht First Nations (HFN) are planning to undertake the construction of Sarita Bay LNG Export Facility project in British Columbia, Canada.

The project involves the construction of liquefied natural gas (LNG) export facility with a capacity 24 million tonnes per annum (MTPA) comprising 4x6 MTPA.

It includes the construction of storage tanks, loading and unloading facilities, an administrative facility, the installation of machinery and equipment, and the laying of pipelines.

On July 8, 2014, Steelhead and HFN signed an agreement to jointly develop the project.

In February 2015, Steelhead and HFN signed an agreement with WorleyParsons worth of US$30 million.

The scope of the contract covers the provision of environmental, engineering, geotechnical and regulatory services for the proposed project.

In October 2015, the project received approval from council.

In March 2016, Steelhead applied for an export permit with the National Energy Board to transport up to 30 million tonnes of liquefied natural gas per year.

Steelhead is expected to take a final investment decision on the project in 2018 and the project is expected to begin commercial operations in 2022.

Scope

The project involves the construction of LNG export facility with a capacity 24MTPA comprising 4x6 MTPA in British Columbia, Canada.

The US$28,144 million project includes the following:

1. Construction of storage tanks

2. Construction of loading and unloading facilities

3. Construction of an administrative facility

4. Installation of machinery and equipment

5. Laying of pipelinesReasons To Buy

  • Gain insight into the project.
  • Monitor the latest project developments.
  • Identify key project contacts.


Download our eBook: How to Succeed Using Market Research

Learn how to effectively navigate the market research process to help guide your organization on the journey to success.

Download eBook

Share this report

;