Market Research Logo

SERD/Marubeni/GDF – Rantau Dedap Geothermal Power Plant 240 MW – South Sumatra - Project Profile

SERD/Marubeni/GDF – Rantau Dedap Geothermal Power Plant 240 MW – South Sumatra - Project Profile

Synopsis

"SERD/Marubeni/GDF – Rantau Dedap Geothermal Power Plant 240 MW – South Sumatra - Project Profile" contains information on the scope of the project including project overview and location. The profile also details project ownership and funding, gives a full project description, as well as information on contracts, tendering and key project contacts.

The "SERD/Marubeni/GDF – Rantau Dedap Geothermal Power Plant 240 MW – South Sumatra - Project Profile" is part of Timetric's database of 82,000+ construction projects. Our database includes a 10+ year archive of completed projects, full coverage of all global projects with a value greater than $25 million and key contact details for project managers, owners, consultants, contractors and bidders.

Summary

PT Supreme Energy Rantau Dedap (SERD), Marubeni Corporation and GDF SUEZ are jointly planning to undertake the construction of Rantau Dedap Geothermal Power Plant project in South Sumatra, Indonesia.

The project involves the construction of a 240 MW geothermal power plant comprises in two units. It includes the construction of a geothermal power generation unit, a cooling tower, a distributed control center, a turbine control room, a motor control room, electrical equipment rooms, a substation, an engine room, traveling derrick.

It also includes the drilling of five 2,400m-deep wells, and the installation of geothermal steam turbines, generators, direct contact condensers, hot-well pumps, a geothermal turbo generator and mechanical equipment.

The project will be developed in stages. The first stage will have a capacity of 86MW.

Jacobs Consultancy (formerly known as PT. Sinclair Knight Merz) has been appointed as pre-feasibility study consultant, PT. Wiratman as surveyor and AECOM as the consulting engineer.

In March 2009, SERD completed the pre-feasibility study. In 2011, the exploration program was commenced.

In February 2012, heat loss survey, report, and the geoscientific interpretation works completed.

On November 12, 2012, SERD entered into a Power Purchase Agreement (PPA) with Indonesian state-owned electricity utility, Perusahaan Listrik Negara (PLN).

In January 2013, PT Leighton Contractors Indonesia secured US$32 million, 18-month contract for civil infrastructure works. The scope of contract covers the upgrade and widening of 14km of existing roads, the construction of 35km of ‘green field’ access roads, five well pads for drilling works, including drainage and pumps, supplying and installing 19km of water/brine distribution pipeline, a water supply intake and associated pumps and construction of camp accommodation for 250 staff and workers.

On February 3, 2014, the spud-in exploration drilling works on first well RD-B1 commenced and completed by the end of March 2014. It was then followed by the drilling of the second well RD-B2 that was completed in May 2014.

In July 2014, Asian Development Bank (ADB) agreed to fund US$50 million with the support of Clean Technology Fund for the development of the project.

SERD completed drilling of third well RD-C1 in September 2014, and that of fourth well RD-I1 was completed in late 2014.

In November 2014, SERD and ADB held a press conference that confirmed SERD fulfilled all conditions precedent and reached financial closing.

In March 2016, exploration survey and land acquisition activities were completed.

Construction works on the first stage is scheduled to complete in 2019.

Scope

The project involves the construction of a 240 MW geothermal power plant in South Sumatra, Indonesia.

The US$800 million project includes the following:

1. Construction of a geothermal power generation unit

2. Construction of a cooling tower

3. Construction of a distributed control center

4. Construction of a turbine control room

5. Construction of a motor control room

6. Construction of an electrical equipment room

7. Construction of a substation, drilling of five 2,400m-deep wells

8. Construction of infrastructure works

9. Installation of geothermal steam turbines

10. Installation of direct contact condensers

11. Installation of hot-well pumps

12. Installation of geothermal turbo generator and mechanical equipment

13. Drilling of five wells

Reasons To Buy

  • Gain insight into the project.
  • Monitor the latest project developments.
  • Identify key project contacts.


1.Key Statistics
2.Key Dates
3.Sector
4.Operating metrics
5.Tender Information
6.Scope
7.Description
8.Latest update
9.Background
10.Key Contacts
11.General News, Project News
12.Appendix

Download our eBook: How to Succeed Using Market Research

Learn how to effectively navigate the market research process to help guide your organization on the journey to success.

Download eBook

Share this report