"Pospower – Samcheok Coal-Fired Power Plant 2000 MW – Gangwon Province - Project Profile" contains information on the scope of the project including project overview and location. The profile also details project ownership and funding, gives a full project description, as well as information on contracts, tendering and key project contacts.

The "Pospower – Samcheok Coal-Fired Power Plant 2000 MW – Gangwon Province - Project Profile" is part of Timetric's database of 82,000+ construction projects. Our database includes a 10+ year archive of completed projects, full coverage of all global projects with a value greater than $25 million and key contact details for project managers, owners, consultants, contractors and bidders.

Summary

Pospower Co., Ltd (Pospower), a subsidiary of POSCO Energy, is planning to undertake the construction of a new coal-fired power plant project in Gangwon Province, Republic of Korea.

The project involves the construction of a 2,000MW coal-fired power plant comprising two units, each with a power generating capacity of 1,000MW.

The project includes the construction of a powerhouse, substation, raw water storage tanks and coal storage unit, the installation of supercritical circulating fluidized-bed (CFB) boilers, steam turbines and generators, and the laying of water transmission pipelines.

On June 7, 2013, Before the acquisition of plant by Pospower, KEPCO E&C has signed the Owner’s Engineering Service Agreement with Tongyang Power consortium.

The scope of the contract covers the conceptual design, EPC bidding guide generation, review and approval of documents submitted by special purpose corporation (SPC) contractor, and support of power plant construction permission and approval.

KDB Bank will provide funds for the project implementation.

In November 2015, Doosan Heavy Industries has been selected as the preferred bidder for equipment supply contract.

On March 22, 2017, the project secured the approval Ministry of Industry, Trade, and Energy for the construction plan.

In December 2017, the Ministry of Environment accepted the Environmental Impact Assessment (EIA).

POSCO E&C and Doosan Heavy Industries & Construction were appointed as the construction contractors.

Pospower is planning to commence the construction in April 2018 and scheduled to complete by 2021.

Scope

The project involves the construction of a 2,000MW coal-fired power plant in Samcheok, Gangwon Province, Republic of Korea.

The US$2,900 million project includes the following:

1. Construction of a powerhouse

2. Construction of a substation

3. Construction of raw water storage tanks

4. Construction of a coal storage unit

5. Laying of water transmission pipelines

6. Installation of super-critical circulating fluidized-bed (CFB) boilers

7. Installation of steam turbines

8. Installation of generatorsReasons To Buy

  • Gain insight into the project.
  • Monitor the latest project developments.
  • Identify key project contacts.


1.Key Statistics
2.Key Dates
3.Sector
4.Operating metrics
5.Tender Information
6.Scope
7.Description
8.Latest update
9.Background
10.Key Contacts
11.General News, Project News
12.Appendix

Download our eBook: How to Succeed Using Market Research

Learn how to effectively navigate the market research process to help guide your organization on the journey to success.

Download eBook

Share this report