"PRE – Marten Ridge Wind Farm 80 MW – British Columbia - Project Profile" contains information on the scope of the project including project overview and location. The profile also details project ownership and funding, gives a full project description, as well as information on contracts, tendering and key project contacts.
The "PRE – Marten Ridge Wind Farm 80 MW – British Columbia - Project Profile" is part of Timetric's database of 82,000+ construction projects. Our database includes a 10+ year archive of completed projects, full coverage of all global projects with a value greater than $25 million and key contact details for project managers, owners, consultants, contractors and bidders.
Summary
Premier Renewable Energy (PRE), an independent power company registered in Victoria, is planning to undertake the Marten Ridge Wind Farm project approximately 10km northeast of Fernie, British Columbia in the Regional District of East Kootenay, Canada
The project involves the construction of 80MW onshore wind farm with 40 wind turbines of capacity 2MW each.
The project will include the construction of an interconnecting collector system, a substation and 15km of new access roads.
The project will include the construction related facilities like operation and maintenance building, power controlling systems, the installation of electric feeder system, wind turbines, and the laying of underground transmission lines and an overhead transmission line that will connect to the existing inter-connection point at Spenser Bridge.
In May 2016, Environmental Assessment Office (EAO) has withdrawn the project from Environmental Assessment (EA).
Planning activities are underway.
Scope
The project involves the construction of a 80MW wind power plant in Fernie, British Columbia.
The US$172 million project includes the following:
1. Construction of a 80MW wind farm
2. Construction of an interconnecting collector system
3. Installation of 40 wind turbines of 2MW capacity each
4. Installation of nacelles
5. Installation of wind electric converters
6. Installation of electric feeder system
7. Construction of a substation
8. Construction of an operation and maintenance building
9. Construction of access roads
10. Installation of overhead transmission line
11. Construction of related facilities