Market Research Logo

PEL – Palmdale Gas-Fired Combined Cycle Power Plant 650 MW – California - Project Profile

PEL – Palmdale Gas-Fired Combined Cycle Power Plant 650 MW – California - Project Profile

Synopsis

"PEL – Palmdale Gas-Fired Combined Cycle Power Plant 650 MW – California - Project Profile" contains information on the scope of the project including project overview and location. The profile also details project ownership and funding, gives a full project description, as well as information on contracts, tendering and key project contacts.

The "PEL – Palmdale Gas-Fired Combined Cycle Power Plant 650 MW – California - Project Profile" is part of Timetric's database of 82,000+ construction projects. Our database includes a 10+ year archive of completed projects, full coverage of all global projects with a value greater than $25 million and key contact details for project managers, owners, consultants, contractors and bidders.

Summary

Palmdale Energy LLC (PEL), a solely owned subsidiary of Summit Power Project Holdings LLC, is planning to construct a hybrid power plant in California, the US.

The project involves the construction of a 650MW combined-cycle power plant on a 20.2ha.

It includes the construction of a powerhouse, an operations building, gas storage tanks and a substation, the installation of two SGT6-5000F natural gas-fired combustion turbine generators (CTGs) rated at 220MW each, two heat recovery steam generators (HRSG), a steam turbine-generator rated at 232MW, an auxiliary boiler, an air cooled condenser, a turbine inlet evaporative cooler, two 49m high, 6.7m diameter HRSG exhaust stacks and auxiliary equipment and laying of transmission lines.

Galati & Blek LLP has been appointed as legal advisor and Atmospheric Dynamics, Inc. as the environmental consultant.

Siemens AG has been appointed as turbine supply contractor and Aecom as planning consultant for the project.

In February 2016, California Energy Commission Committee (CECC) assigned to conduct proceedings on the Petition to Amend Certification for the project and scheduled a public Committee Status Conference to review the progress.

On March 23, 2016, a preliminary staff assessment (PSA) was issued by the California Energy Commission staff on the project's Petition to Amend (PTA).

The PSA examined engineering, environmental, public health and safety aspects of the project, based on the information provided by applicant PEL and other sources available at the time the PSA was prepared.

On May 18, 2016, PEL applies to CECC for extension of the start of construction deadline for approximately 9 months, from August 10, 2016, to June 1, 2017.

In July 2016, CECC approved the extension of the start of construction deadline for approximately 9 months, from August 10, 2016, to June 1, 2017.

On September 12, 2016, the Final Staff Assessment (FSA) report was issued to CECC by California Energy Commission staff for the project's PTA.

On March 10, 2017, CECC held a Prehearing Conference on the project's PTA.

On March 22, 2017, CECC held a an Evidentiary hearing on the project's PTA.

CECC is in the process of reviewing the project's PTA.

Scope

The project involves the construction of a 650MW combined cycle power plant on 20.2ha of land in Palmdale, California, the US.

The US$800 million project includes the following:

1. Construction of a powerhouse and a substation

2. Construction of an operations building

3. Construction of gas storage tanks

4. Installation of an auxiliary boiler

5. Installation of gas turbines

6. Installation of two SGT6-5000F natural gas-fired CTGs

7. Installation of two heat recovery steam generators

8. Installation of a steam turbine-generator

9. Installation of an air-cooled condenser

10. Installation of a turbine inlet evaporative cooler

11. Installation of two 49m high, 6.7m diameter HRSG exhaust stacks

12. Installation od auxilary equipment

13. Laying of transmission lines

Reasons To Buy

  • Gain insight into the project.
  • Monitor the latest project developments.
  • Identify key project contacts.


1.Key Statistics
2.Key Dates
3.Sector
4.Operating metrics
5.Tender Information
6.Scope
7.Description
8.Latest update
9.Background
10.Key Contacts
11.General News, Project News
12.Appendix

Download our eBook: How to Succeed Using Market Research

Learn how to effectively navigate the market research process to help guide your organization on the journey to success.

Download eBook

Share this report