Market Research Logo

NPT/Hydro Quebec – Northern Pass Transmission Line – Canada - Project Profile

NPT/Hydro Quebec – Northern Pass Transmission Line – Canada - Project Profile

Synopsis

"NPT/Hydro Quebec – Northern Pass Transmission Line – Canada - Project Profile" contains information on the scope of the project including project overview and location. The profile also details project ownership and funding, gives a full project description, as well as information on contracts, tendering and key project contacts.

The "NPT/Hydro Quebec – Northern Pass Transmission Line – Canada - Project Profile" is part of Timetric's database of 82,000+ construction projects. Our database includes a 10+ year archive of completed projects, full coverage of all global projects with a value greater than $25 million and key contact details for project managers, owners, consultants, contractors and bidders.

Summary

Northern Pass Transmission LLC (NPT) a joint venture of Eversource Energy and NStar, in partnership with Hydro-Quebec, are planning to undertake the construction of Northern Pass Transmission Line that will connect the Des Cantons substation in Quebec with southern New Hampshire, the US.

The project involves the construction of approximately a 300km transmission line that will deliver 1,200MW of power.

It includes the construction of a 51.90km of new overhead right-of-way transmission line and a 12.47km of new underground right-of-way line in northern New Hampshire.

The underground transmission line will include two sections, a 701m section for the Route 3 crossing in Pittsburg and Clarksville and a 12km section within town and state road corridors in portions of Stewartstown and Clarksville.

Burns and McDonnell Engineering Company Inc. was appointed as engineering and design consultant and M.J. Electric LLC was appointed as engineering consultant.

ABB was appointed as engineering consultant who will undertake the engineering and fabrication works on the underground DC cable and the converter station in Franklin and equipment at the Deerfield substation for interconnecting the Northern Pass line to the regional electrical grid.

In May 2009, The U.S. Federal Energy Regulatory Commission (FERC) approved a funding plan and in February 2011, FERC approved the Transmission Service Agreement for the project.

In October 2010, the Presidential Permit application was submitted to The U.S. Department of Energy (DOE) and The DOE held held public scoping meetings in seven locations in New Hampshire between March 14 and March 20, 2011.

On April 12, 2011, a letter was submitted to DOE, withdrawing support for some routing alternatives. The letter also requested an extension of the public scoping period for the identification of an improved route and to allow for additional public comment.

The DOE held four public scoping meetings throughout the state between September 23 and September 26, 2013.

Draft Environmental Impact Statement (EIS) was released by the DOE in July 2015.

As of August 19, 2015, NPT is in process of releasing a new proposed route for the project.

On October 19, 2015, NPT submitted an application for siting approval to New Hampshire Site Evaluation Committee (SEC).

In April 2016, subject to regulatory approvals, PAR Electrical Contractors Inc. will be appointed as construction contractor.

In June 2017, New Hampshire Public Utilities Commission (PUC) has approved a request by NPT to cross public waters and public lands for the construction of the project, stating the crossings will not interfere with the public use of the land and waters affected by the crossings.

NPT is in the process of seeking necessary approvals.

Scope

The project involves the construction of a 300km high voltage direct current (HVDC) power transmission line from the Des Cantons substation in Quebec to New England, the US.

The US$1,400 million project includes the following:

1. Construction of a 51.90km of new overhead right-of-way transmission line

2. Construction of a 12.47km of new underground right-of-way line

3. Construction of substations

4. Installation of transformers

5. Construction of related infrastructure facilities

Reasons To Buy

  • Gain insight into the project.
  • Monitor the latest project developments.
  • Identify key project contacts.


1.Key Statistics
2.Key Dates
3.Sector
4.Operating metrics
5.Tender Information
6.Scope
7.Description
8.Latest update
9.Background
10.Key Contacts
11.General News, Project News
12.Appendix

Download our eBook: How to Succeed Using Market Research

Learn how to effectively navigate the market research process to help guide your organization on the journey to success.

Download eBook

Share this report