Market Research Logo

MoTC – Al Duqm Airport – Al Wusta - Project Profile

MoTC – Al Duqm Airport – Al Wusta - Project Profile

Synopsis

"MoTC – Al Duqm Airport – Al Wusta- Project Profile" contains information on the scope of the project including project overview and location. The profile also details project ownership and funding, gives a full project description, as well as information on contracts, tendering and key project contacts.

The "MoTC – Al Duqm Airport – Al Wusta- Project Profile" is part of Timetric's database of 82,000+ construction projects. Our database includes a 10+ year archive of completed projects, full coverage of all global projects with a value greater than $25 million and key contact details for project managers, owners, consultants, contractors and bidders.

Summary

The Oman Ministry of Transport and Communication (MoTC) is undertaking the Al Duqm Airport project in Oman.

The project involves the construction of a new airport on a 2,700ha of land. The project is being executed in three packages.

Package I includes the construction of roadways and other utilities.

Package II includes the construction of runways and the airfield infrastructure.

Package III includes the construction of a 5,700m2 passenger terminal which can process 500,000 passengers a year, a 37m high air traffic control (ATC) tower and a 8,000m2 air cargo terminal which can handle 25,000 tonnes of cargo per annum, two air bridges, four remote aircraft stands, 4km long runway, two link aircraft taxiways, roads, fuel station, and the installation of runway lighting systems, aircraft fuelling system and related equipment.

The ATC tower includes a control building, air cargo building, firefighting building, airport maintenance and services equipment building, and the central services building, central cooling unit, the generators and the power transformers. It includes the construction of 31,500m2 parking area.

In December 2006, Parsons International was appointed as a design consultant.

In October 2008, Desert Line Projects was appointed as EPC contractor on first package and Hanjin Heavy Industries & Construction Co., Ltd on the second package.

On July 1, 2009, Ibn Khaldun Almadaen Engineering Consultants was appointed as supervision and management consultant and on July 24, 2009, Aeroports de Paris Ingenierie (ADPi) was awarded the PMC contract.

In January 2011, MoTC invited bids from the interested companies to compete for the construction contract with March 7, 2011, as the submission deadline. The deadline was later extended four times and the final deadline was set as June 6, 2011.

Three companies including Larsen & Toubro (Oman), the joint venture of Galfar and Daewoo Engineering, and Consolidated Contractors Co have registered their interest in the proposed project; however, the tender was cancelled in August 2012.

In October 2012, the engineering designs work for the domestic passenger terminals were completed.

In February 2013, construction works on the package I completed.

In December 2013, Oman Special Economic Zone Authority (Sezad) invited tenders for the main building works (Package III) with the bid submission due date as January 19, 2014.

In December 2013, construction works on package II completed.

In June 2014, Larsen & Toubro (Oman) LLC was appointed as EPC contractor on Package III. The value of the contract is US$91 million.

Oman Airports Management Company S.A.O.C (OAMC), owned by the Government of the Sultanate of Oman, is responsible for the management and operation of the airport.

Construction works on package III are underway.

Scope

The project involves the construction of a new airport on a 2,700ha of land in Oman.

The US$200 million project includes the following:

1. Construction of 5,700m2 passenger terminal which can process 500,000 passengers a year

2. Construction of runways

3. Construction of airfield infrastructure

4. Construction of roadways and utilities

5. Construction of car 31,500m2 parking area

6. Construction of reservoir for treated effluents

7. Construction of 37m high air traffic control (ATC) tower

8. Construction of air cargo terminal

9. Construction of a control building

10. Construction of an air cargo building

11. Construction of firefighting building

12. Construction of services equipment building

13. Construction of central services building

14. Construction of central cooling unit

15. Construction of final layers of the 4km-long runway

16. Construction of two link aircraft taxiways

17. Construction of two air bridges

18. Construction of fuel station and roads

19. Construction of 8,000m2 air cargo terminal which can handle 25,000 tonnes of cargo per annum

20. Construction of four remote aircraft stands

21. Installation of generators

22. Installation of power transformers

23. Installation of runway lighting systems

24. Installation of aircraft fuelling system

25. Installation of required equipment

Reasons To Buy

  • Gain insight into the project.
  • Monitor the latest project developments.
  • Identify key project contacts.


1.Key Statistics
2.Key Dates
3.Sector
4.Operating metrics
5.Tender Information
6.Scope
7.Description
8.Latest update
9.Background
10.Key Contacts
11.General News, Project News
12.Appendix

Download our eBook: How to Succeed Using Market Research

Learn how to effectively navigate the market research process to help guide your organization on the journey to success.

Download eBook

Share this report