"Kolin/Kalyon/Celikler – Cayirhan B Coal Fired Power Plant 800 MW – Turkey - Project Profile" contains information on the scope of the project including project overview and location. The profile also details project ownership and funding, gives a full project description, as well as information on contracts, tendering and key project contacts.

The "Kolin/Kalyon/Celikler – Cayirhan B Coal Fired Power Plant 800 MW – Turkey - Project Profile" is part of Timetric's database of 82,000+ construction projects. Our database includes a 10+ year archive of completed projects, full coverage of all global projects with a value greater than $25 million and key contact details for project managers, owners, consultants, contractors and bidders.

Summary

The Kolin-Kalyon Enerji Çelikler Joint Venture Group plans to undertake the construction of a coal-fired power plant in Nallihan district, Ankara Province, Turkey.

The project involves the construction of an 800MW coal-fired plant. It includes the construction of a fuel storage unit, combustion chambers, chimneys, powerhouse, cooling units, switch yard, coal storage and washing units, and the installation of turbines and generators and the laying of transmission lines.

In August 2016, the development plans were approved by the state government.

In October 2016, tender for the privatization of Cayirhan B area was issued with a bid submission deadline of November 21, 2016.

On February 6, 2017, the Ministry of Energy and Natural Resources, Turkey (MENRT) conducted an open auction process for the privatization of Cayirhan B area.

Four companies namely Fina Enerji Holding, IC Içtas Enerji Yatirim Holding, Kolin-Kalyon Enerji-Çelikler Joint Venture Group and Limak Yatirim Enerji participated in the tender process.

A joint venture Kolin-Kalyon Enerji Çelikler Joint Venture Group won the tender process.

Subject to approvals from the Energy Market Regulatory Authority (EPDK) and the Supreme Council for Privatization (SCP), the MENRT will sign the contract with the selected joint venture group and the state government will grant a 15-year power purchase guarantee on the unit price.

Stakeholder Information:
Planning Authority: Ministry of Energy and Natural Resources, Turkey (MENRT)

Scope

The project involves the construction of a coal-fired power plant with power generation capacity of 800MW in Nallihan district, Ankara Province, Turkey.

The US$1,100 million project includes the following:

1. Construction of a fuel storage unit

2. Construction of combustion chambers

3. Construction of chimneys

4. Construction of powerhouse

5. Construction of cooling units

6. Construction of a switch yard

7. Construction of coal storage and washing units

8. Laying of transmission lines

9. Installation of turbines and generators

10. Installation of safety systems

Reasons To Buy

  • Gain insight into the project.
  • Monitor the latest project developments.
  • Identify key project contacts.


1.Key Statistics
2.Key Dates
3.Sector
4.Operating metrics
5.Tender Information
6.Scope
7.Description
8.Latest update
9.Background
10.Key Contacts
11.General News, Project News
12.Appendix

Download our eBook: How to Succeed Using Market Research

Learn how to effectively navigate the market research process to help guide your organization on the journey to success.

Download eBook

Share this report