"HPPCL – Thana Plaun Hydroelectric Power Plant 191 MW – Himachal Pradesh - Project Profile" contains information on the scope of the project including project overview and location. The profile also details project ownership and funding, gives a full project description, as well as information on contracts, tendering and key project contacts.

The "HPPCL – Thana Plaun Hydroelectric Power Plant 191 MW – Himachal Pradesh - Project Profile" is part of Timetric's database of 82,000+ construction projects. Our database includes a 10+ year archive of completed projects, full coverage of all global projects with a value greater than $25 million and key contact details for project managers, owners, consultants, contractors and bidders.

Summary

Himachal Pradesh Power Corporation Ltd (HPPCL) is planning to construct the Thana Plaun hydroelectric power plant in Himachal Pradesh, India.

The project involves the construction of a 191MW hydroelectric power plant on a 445ha of land.

The project includes the construction of a 107m high RCC dam, an intake structure, a power tunnel system, an underground powerhouse, a tunnel tailrace tunnel and a substation, the installation of generators and transformers and the laying of transmission lines.

The underground powerhouse contains five units of Francis turbines generating 3 x 50.33MW and 2 x 20MW each, with a total design discharge of 229.29m3/s and a net head of about 73m.

In August 2013, the Government of Germany, through its financing agency KfW, agreed to finance around US$278 million for the power plant under Himalaya Hydropower program.

On January 16, 2014, tenders were invited to carry out detailed survey and investigation work with a submission deadline of January 28, 2014.

In February 2014, KfW Group agreed to fund US$278 million for the project.

On June 16, 2014, tenders invited to carry out drilling and drifting works with a submission deadline of June 26, 2014.

Himachal Pradesh government is going to fund the project by providing 20% of equity.

In October 2015, HPCL submitted detailed project report (DPR) to the Central Electricity Authority and the Central Water Commission for the techno-economic clearance.

In April 2016, the HPPCL has requested various consultants and firms for Invitations for Expression of Interests for the project.

Jesco Projects (INDIA) Pvt. Ltd has shown interest in the development.

Scope

The project involves the construction of a 191MW hydroelectric power plant on river Beas, near Mandi, Himachal Pradesh, India.

The US$300 million project includes the following:

1. Construction of a 107m high RCC dam

2. Construction of an intake structure

3. Construction of a power tunnel system

4. Construction of an underground powerhouse

5. Construction of a net head of about 73m

6. Construction of a substation

7. Installation of five Francis turbines

8. Installation of generators

9. Installation of transformers

10. Laying of the transmission lines

11. Construction of related infrastructure

Reasons To Buy

  • Gain insight into the project.
  • Monitor the latest project developments.
  • Identify key project contacts.


1.Key Statistics
2.Key Dates
3.Sector
4.Operating metrics
5.Tender Information
6.Scope
7.Description
8.Latest update
9.Background
10.Key Contacts
11.General News, Project News
12.Appendix

Download our eBook: How to Succeed Using Market Research

Learn how to effectively navigate the market research process to help guide your organization on the journey to success.

Download eBook

Share this report