GoHP – Purthi Hydroelectric Power Plant 300 MW – Himachal Pradesh - Project Profile

GoHP – Purthi Hydroelectric Power Plant 300 MW – Himachal Pradesh - Project Profile

Synopsis

"GoHP – Purthi Hydroelectric Power Plant 300 MW – Himachal Pradesh - Project Profile" contains information on the scope of the project including project overview and location. The profile also details project ownership and funding, gives a full project description, as well as information on contracts, tendering and key project contacts.

The "GoHP – Purthi Hydroelectric Power Plant 300 MW – Himachal Pradesh - Project Profile" is part of Timetric's database of 82,000+ construction projects. Our database includes a 10+ year archive of completed projects, full coverage of all global projects with a value greater than $25 million and key contact details for project managers, owners, consultants, contractors and bidders.

Summary

The Government of Himachal Pradesh (GoHP) is planning to construct a hydroelectric power plant in Himachal Pradesh, India.

The project involves a construction of a 300MW hydroelectric power plant.

It includes the construction of a powerhouse, a substation, and related infrastructure, the installation of turbines, transformers and generators, and the laying of transmission lines.

Purthi Power Pvt Ltd, a subsidiary of Purthi Group, has been appointed by GoHP as a developer.

In November 2012, the GoHP submitted the project for the environmental clearance.

On March 23, 2013, the Expert Appraisal Committee rejected the project.

In February 2015, the GoHP submitted a revised proposal of Purthi HEP for 210 MW capacity.

In May 2016, the Expert Appraisal Committee recommended first stage clearance for 210 MW of the project.

Scope

The project involves the construction of a 300MW hydroelectric power plant in Lahaul and Spiti district, Himachal Pradesh, India.

The US$340 million project includes the following:

1. Construction of a powerhouse

2. Construction of a substation

3. Installation of transformers and generators

4. Installation of turbines

5. Laying of transmission lines

Reasons To Buy

  • Gain insight into the project.
  • Monitor the latest project developments.
  • Identify key project contacts.


1.Key Statistics
2.Key Dates
3.Sector
4.Operating metrics
5.Tender Information
6.Scope
7.Description
8.Latest update
9.Background
10.Key Contacts
11.General News, Project News
12.Appendix

Download our eBook: How to Succeed Using Market Research

Learn how to effectively navigate the market research process to help guide your organization on the journey to success.

Download eBook

Share this report