"GoAP – Siyom Hydroelectric Power Plant 1000 MW – Arunachal Pradesh - Project Profile" contains information on the scope of the project including project overview and location. The profile also details project ownership and funding, gives a full project description, as well as information on contracts, tendering and key project contacts.

The "GoAP – Siyom Hydroelectric Power Plant 1000 MW – Arunachal Pradesh - Project Profile" is part of Timetric's database of 82,000+ construction projects. Our database includes a 10+ year archive of completed projects, full coverage of all global projects with a value greater than $25 million and key contact details for project managers, owners, consultants, contractors and bidders.

Summary

The Government of Arunachal Pradesh (GoAP) is planning to construct a hydroelectric power plant in Arunachal Pradesh, India.

The project involves the construction of a 1,000MW hydroelectric power plant comprising six units of 166.7MW each.

It will include the construction of a powerhouse, substations, access roads, a 155m concrete dam, diversion tunnels with upstream and downstream coffer dam, concrete lined head race tunnel, steel line shaft and tail race tunnel, the installation of turbines, transformers and generators, and the laying of transmission lines.

The project is planned to be implemented through public-private partnership (PPP) mode on build-own-operate-transfer basis (BOOT) basis.

Energy Infratech Pvt. Ltd has been appointed as owner's engineer.

In February 2006, Reliance Power Ltd (RPOWER) signed a memorandum of understanding with (MoU) with GoAP to build the power plant on BOOT basis for a concession period of 40 years.

RPOWER formed a special purpose vehicle (SVP), Siyom Hydro Power Pvt. Ltd (SHPPL), to execute and operate the power plant.

On March 31, 2008, project received environmental clearance from the Ministry of Environment and Forests (MoEF).

In October 2010, SHPPL submitted detailed project report (DPR) to the Central Electricity Authority.

In June 2011, the forest advisory committee (FAC) of the MoEF insisted to study the cumulative impact of hydroelectric project.

In April 2015, FAC of the MoEF denied diversion of 1,502.30ha of forest land for the construction of hydroelectric power plant.

In August 2016, public hearing was held.

SHPPL is waiting for necessary approvals from FAC of the MoEF.

Scope

The project involves the construction of 1,000MW hydroelectric power plant on the Siyom River near Raying in West Siang district, Arunachal Pradesh, India.

The US$1,788 million project includes the following:

1. Construction of a 166.7MW hydroelectric power plant under first unit

2. Construction of a 166.7MW hydroelectric power plant under second unit

3. Construction of a 166.7MW hydroelectric power plant under third unit

4. Construction of a 166.7MW hydroelectric power plant under fourth unit

5. Construction of a 166.7MW hydroelectric power plant under fifth unit

6. Construction of a 166.7MW hydroelectric power plant under sixth unit

7. Construction of a 155m concrete dam

8. Installation of turbines

9. Installation of generators and transformers

10. Laying of transmission lines

Reasons To Buy

  • Gain insight into the project.
  • Monitor the latest project developments.
  • Identify key project contacts.


1.Key Statistics
2.Key Dates
3.Sector
4.Operating metrics
5.Tender Information
6.Scope
7.Description
8.Latest update
9.Background
10.Key Contacts
11.General News, Project News
12.Appendix

Download our eBook: How to Succeed Using Market Research

Learn how to effectively navigate the market research process to help guide your organization on the journey to success.

Download eBook

Share this report