Market Research Logo

EVN – O Mon Power Complex 2910 MW – Mekong Delta - Project Profile

EVN – O Mon Power Complex 2910 MW – Mekong Delta - Project Profile

Synopsis

"EVN – O Mon Power Complex 2910 MW – Mekong Delta - Project Profile" contains information on the scope of the project including project overview and location. The profile also details project ownership and funding, gives a full project description, as well as information on contracts, tendering and key project contacts.

The "EVN – O Mon Power Complex 2910 MW – Mekong Delta - Project Profile" is part of Timetric's database of 82,000+ construction projects. Our database includes a 10+ year archive of completed projects, full coverage of all global projects with a value greater than $25 million and key contact details for project managers, owners, consultants, contractors and bidders.

Summary

Vietnam Electricity (EVN) along with Power Generation Corporation 2, is undertaking the construction of O Mon power complex project in Mekong Delta, Vietnam.

The project involves the construction of four power plants to operate as a combined-cycle power plant with a total capacity of 2,910MW on 162ha area.

It includes the construction of a powerhouse, access roads, a gas distribution center, docks, water intakes and related facilities and installation of switchyards, safety systems and cooling water discharge channels.

First power plant of O Mon power complex (O Mon I) includes the construction of two power units with the capacity of 330MW each.

Can Tho Thermal Power Company Ltd was appointed as PMC contractor for the project.

Unit I of O Mon I:

It involves the construction of a 330MW power plant.

In late 2005, Mitsubishi Heavy Industries Ltd (MHI) and LILAMA were appointed as turnkey contractors.

MHI has been appointed to supply boilers and steam turbines while Toa Corporation to undertake the civil construction work and Tokyo Electric Power Services Co., Ltd as the design consultant.

LILAMA 45.1 Joint Stock Company was appointed to undertake fabrication of mechanical equipment and steel structures, the installation of mechanical equipment, construction of temporary items, supporting services, commissioning and handover, and receiving, transportation, storage, preservation and handling of materials on site.

In June 2009, construction work on the first unit was completed.

Unit II of O Mon I:

It involves the construction of a 330MW power plant.

On August 16, 2012, the EPC contract was awarded to a consortium of Sojitz Corporation and Daelim Industrial Co., Ltd.

On October 30, 2012, MHI received a contract to supply a steam turbine and a boiler.

Second power plant (O Mon II) includes the construction of a 750MW power unit while the third power plant (O Mon III) a 750MW power unit and the fourth power plant (O Mon IV) includes a 750MW power unit.

Asian Development Bank (ADB) has been appointed as technical consultant for providing technical assistance for private sector financing following a transparent competitive bidding process for O Mon II and O Mon III and for arranging financing for the O Mon IV power plant.

On February 11, 2015, ADB prepared the pre-qualification bidding documents for O Mon II and O Mon III.

As of March 2015, pre-qualification bidding documents for O Mon II and O Mon III were awaiting approval and progress on the project is slow.

In August 2015, ADB completed the funding process and assisted in arranging funds of US$370 million from KfW Bankengruppe for the O Mon IV.

In the fourth quarter of 2015, construction works on Unit II of O Mon I were completed.

In January 2017, development of III and IV units has been approved by the Ministry of Industry and Trade to revise the Master Plan.

Planning activities O Mon II, III and IV underway and construction on the whole project is expected to be completed by 2022.

Scope

The project involves the construction of four power plants to operate as a combined cycle power plant with a total capacity of 2,910MW at O Mon in Can Tho, Mekong Delta, Vietnam.

The US$2,000 million project includes the following:

1. Construction of 2×330MW power plant I

2. Construction of gas-fired 750MW O Mon II

3. Construction of gas-fired 750MW O Mon III

4. Construction of gas-fired 750MW O Mon IV

5. Construction of a powerhouse

6. Construction of access roads

7. Construction of a gas distribution center

8. Construction of docks

9. Construction of water intakes

10. Installation of safety systems

11. Installation of switchyards

12. Construction of related facilities

Reasons To Buy

  • Gain insight into the project.
  • Monitor the latest project developments.
  • Identify key project contacts.


1.Key Statistics
2.Key Dates
3.Sector
4.Operating metrics
5.Tender Information
6.Scope
7.Description
8.Latest update
9.Background
10.Key Contacts
11.General News, Project News
12.Appendix

Download our eBook: How to Succeed Using Market Research

Learn how to effectively navigate the market research process to help guide your organization on the journey to success.

Download eBook

Share this report