Market Research Logo

DLL – Driftwood LNG Terminal – Louisiana - Project Profile

DLL – Driftwood LNG Terminal – Louisiana - Project Profile

Synopsis

"DLL – Driftwood LNG Terminal – Louisiana - Project Profile" contains information on the scope of the project including project overview and location. The profile also details project ownership and funding, gives a full project description, as well as information on contracts, tendering and key project contacts.

The "DLL – Driftwood LNG Terminal – Louisiana - Project Profile" is part of Timetric's database of 82,000+ construction projects. Our database includes a 10+ year archive of completed projects, full coverage of all global projects with a value greater than $25 million and key contact details for project managers, owners, consultants, contractors and bidders.

Summary

Driftwood LNG LLC, (DLL) a subsidiary of Tellurian Inc. (TELL) is planning to build an LNG terminal in Calcasieu Parish, Louisiana, the US.

The project involves the construction of an LNG terminal with a capacity of 26 MTPA of LNG (million tonnes per annum) on 323.7ha of land. It includes the construction of five LNG trains, gas processing units, vacuum chambers, distillation units, four storage tanks with a capacity of 175,000m3 each, three compressor stations, 15m stations and other related infrastructure facilities, and the laying of 154.5km gas pipelines, a 5.6km 36-inch-diameter pipeline lateral.

The 154.5km pipeline will be constructed in three segments consists of 119km 42-inch diameter pipeline, 17.7km 42-inch diameter pipeline, and 17.7km 36-inch diameter pipeline.

On June 6, 2016, The Federal Energy Regulatory Commission (FERC) approved the pre-filing request.

On July 8, 2017, DLL filed a draft resource reports with FERC.

On October 4, 2017, FERC scheduled a public comment session.

On October 13, 2016, DLL filed an application for authorization to export LNG with the FERC.

On March 2, 2017, DLL received the LNG export approvals.

On March 10, 2017, DLL appointed SG Americas Securities LLC, a unit of Societe Generale as a financial advisor for Driftwood LNG project.

On April 3, 2017, DLL submitted a formal application to FERC.

DLL and Driftwood Pipeline LLC have completed the pre-filing phase of the project.

On August 9, 2017, Bechtel completed the front-end engineering and design study (FEED) and submitted engineering, procurement, and construction (EPC) proposal for the project.

DLL is expected to sign a binding EPC agreement with Bechtel in the fourth quarter of 2017 and achieve financial close in the third quarter of 2018.

Construction is expected to commence in the third quarter of 2018 and scheduled to complete by 2022.

Scope

The project involves the construction of an LNG terminal with a capacity of 26 MTPA on 323.7ha of land in Calcasieu Parish, Louisiana, the US.

The US$16,000 million project includes the following:

1. Construction of five LNG trains

2. Construction of gas processing units

3. Construction of vacuum chambers

4. Construction of distillation units

5. Construction of four storage tanks with a capacity of 175,000m3 each

6. Construction of 15m stations

7. Construction of related infrastructure facilities

8. Laying of a 5.6km 36-inch-diameter pipeline

9. Laying of 154.5km gas pipelines

Reasons To Buy

  • Gain insight into the project.
  • Monitor the latest project developments.
  • Identify key project contacts.


1.Key Statistics
2.Key Dates
3.Sector
4.Operating metrics
5.Tender Information
6.Scope
7.Description
8.Latest update
9.Background
10.Key Contacts
11.General News, Project News
12.Appendix

Download our eBook: How to Succeed Using Market Research

Learn how to effectively navigate the market research process to help guide your organization on the journey to success.

Download eBook

Share this report